Pompano Beach AC Replacement Permit Guide
Replacing an air conditioner in the City of Pompano Beach is handled by the Building Inspections Division of the Department of Development Services. This guide summarizes the city's own A/C change-out checklist, fee schedule, and permit process, with a link to each document so you can check it yourself.
When is a permit required?
- A Mechanical Permit is required for the installation, alteration, or major repair of any residential or commercial air conditioning system. A permit is not required for minor part replacements that do not affect the system's approval or safety.[1]
- The city's A/C Changeout checklist covers system changeouts (replacements) only, not the addition of new units. New installs, mini splits, and replacements where the configuration or layout changes also need Building, Electrical, and Zoning Compliance applications.[1],[2]
- Florida's HB 803 small-project exemption does not apply: the city lists HVAC installation, replacement, or repair as mechanical work that always requires a permit, regardless of cost.[7]
What to submit
- A Mechanical Permit Application from a licensed mechanical contractor.[1],[2]
- If you're an owner-builder using the Florida Statute 489.103 exemption: a completed Owner/Builder Statement Affidavit. The owner-builder option is not available for work in condominiums.[2]
- The completed Broward County Uniform Data Form for Residential and Light Commercial Air Conditioning Replacements (the A/C Replacement Data Form) — one form per system. It records existing and new unit data and asks whether a new stand, curb, or curb adapter will be installed, whether a duct smoke detector is involved, whether the A/C location stays the same, whether the equipment is being replaced because of a flood, and whether electrical "line side" work is needed.[1],[3]
- An AHRI Certificate for the equipment being installed.[1],[3]
- If existing unit data isn't available, equipment sizing calculations (for example ACCA Manual J or N).[3]
- Attachment (tie-down) details for outdoor equipment, using one of: Florida Product Approval, Miami-Dade NOA, or signed and sealed engineered plans.[1]
- For new installs, mini splits, or a changed configuration or layout: Building and Electrical applications from licensed contractors, and a Zoning Compliance Permit Application.[2]
- If there are trees next to the work: a Tree Permit Application with a Tree Protection Plan and Tree Protection Detail.[2]
- A Notice of Commencement is required for heating or air-conditioning replacements with a project value of $15,000 or more. It must be recorded with Broward County; you may upload a copy with the application, but a recorded NOC is required before the first inspection. Florida law exempts direct contracts under $15,000 to repair or replace an existing A/C system.[1],[4]
- Cooling towers, chillers, refrigeration units, and other equipment outside the scope of the residential and light commercial data form must provide plans.[3]
Fees
As published in the city’s fee schedule. Confirm the final amount at submittal — other fees can apply depending on scope.
| Residential A/C change out | $65 up to a 4-ton system, plus $20 for each additional ton or fraction[5] |
|---|---|
| A/C and furnace change out | $70 up to a 4-ton system, plus $20 for each additional ton or fraction[5] |
| Re-review of plans | $100 per hour per plan reviewer[5] |
How review works
Submit the application
Applications go in through the City's ePlan portal. The city's permit process chart also shows paper and permit-expeditor submittals.[7],[6]
Trade review
Not every permit is reviewed by every trade — the Building Division tells applicants which trades must review based on the scope. A straight changeout is a mechanical review; new installs, mini splits, or a changed configuration or layout pull in building, electrical, and zoning applications.[6],[2]
Corrections and resubmittal
If corrections are required, you resubmit corrected plans. Each additional round adds processing time, and re-review fees may apply. The city's process chart notes a 60-day time limitation, after which the application becomes null and void.[6],[5]
Pay fees and obtain the permit
Once approved and fees are paid, the permit is issued.[6]
Mechanical inspections
The city's A/C Changeout checklist lists two mechanical inspections: M ROUGH and M FINAL-MECHANICAL.[1]
Emergency change-outs
When equipment must be replaced or repaired in an emergency, the permit application must be submitted within the next working business day to the Chief Mechanical Inspector, and the city asks you to notify the Chief Mechanical Inspector by email with the job address and contractor before starting the work.[2]
Frequently asked questions
Do I need a permit to replace my AC in Pompano Beach?
Yes. Pompano Beach requires a Mechanical Permit for the installation, alteration, or major repair of any air conditioning system, residential or commercial. Minor part replacements that don't affect the system's approval or safety don't need a permit.
Is an AC replacement under $7,500 exempt under HB 803?
No. The city lists mechanical work — HVAC installation, replacement, or repair — among the work that always requires a permit regardless of cost.
How much is an AC change-out permit in Pompano Beach?
The city's Building Department fee schedule (updated 2/10/26) lists a residential A/C change out at $65 up to a 4-ton system plus $20 for each additional ton or fraction, and an A/C and furnace change out at $70 up to a 4-ton system plus $20 for each additional ton or fraction.
What if my AC fails and needs to be replaced right away?
The city allows emergency replacement: the permit application must be submitted within the next working business day to the Chief Mechanical Inspector, and you should email the Chief Mechanical Inspector with the job address and contractor before starting the work.
Can a homeowner pull their own AC permit in Pompano Beach?
An owner using the Florida Statute 489.103 owner-builder exemption can submit an Owner/Builder Statement Affidavit and assume the contractor's responsibilities. The owner-builder option is not available for work in condominiums.
Do I need a Notice of Commencement for an AC change-out?
Only at $15,000 or more. The city's current A/C Changeout checklist requires a Notice of Commencement for heating or air-conditioning replacements with a project value of $15,000 or more, recorded with Broward County before the first inspection — consistent with Florida law, which exempts A/C repair or replacement contracts under $15,000.
Official sources
- Permit Checklists — A/C ChangeoutCity of Pompano Beach, Building Inspections Division · Last updated 4/28/2026
- Air Conditioner Change Out Checklist (PDF)City of Pompano Beach, Department of Development Services — Building Inspections Division · Updated 10/06/2025
- Broward County Uniform Data Form for Residential and Light Commercial Air Conditioning ReplacementsBroward County Board of Rules & Appeals (Policy 19-02), via City of Pompano Beach · Revised 07/02/2024
- Florida Statutes §713.135 — Notice of commencement and applicability of lienThe Florida Legislature · 2026 Florida Statutes
- Building Department Fee ScheduleCity of Pompano Beach Building Department · Updated 2/10/26
- Department of Development Services: Permit ProcessCity of Pompano Beach
- House Bill 803: Building Permit Exemption for Projects Under $7,500City of Pompano Beach, Development Services
Ask Kodie
Have a question about your ac replacement permit in Pompano Beach? Kodie answers from verified Florida Building Code and local requirements, with citations — or upload your plans for a pre-submittal review.
Ask KodieStuck or rejected? We’ll handle it
We prepare, file, and track permits in Pompano Beach through to issuance — and take over permits already stuck in review.
Get permit helpThis guide summarizes publicly available documents from the permitting authority and is not legal or code advice. Requirements change — always confirm against the current documents linked above and with the building department before you submit. Florida Construction Permitting is a private permit expediting service and is not affiliated with City of Pompano Beach Department of Development Services.