Fort Lauderdale Fence Permit Guide
Fences, walls, and gates in the City of Fort Lauderdale are permitted through the Development Services Department, Building Services. This guide pulls together what the city’s Fence/Wall/Gate Permit Checklist, fee schedule, and online portal guidance say, with a link to each document so you can check it yourself.
When is a permit required?
- The city’s Fence/Wall/Gate Permit Checklist lists a Building permit as the required application, plus an Electrical permit if electrical work (for example, a powered gate) is installed.[1]
- The application is reviewed at the Building and Zoning review stops, Landscaping (not required in the Riverland Road annexed area or the Broward County annexed areas), Electrical if installed, and Engineering if the fence is within an easement.[1]
- Under Florida HB 803, some work on single-family properties under $7,500 can be exempted from a building permit — but the exemption is not automatic. You must submit an exemption request through LauderBuild and wait for a written determination from the Building Official before starting work. Structural work and any property partly or entirely in a Special Flood Hazard Area are excluded, and other requirements such as zoning and setbacks still apply.[3]
What to submit
- A site plan showing the proposed fence, wall, or gate and its setback dimensions to all property lines. This can be omitted if the information is shown on the survey you submit.[1]
- A survey — signed and sealed originals, or two copies with a completed Zoning Affidavit.[1]
- For PVC or metal fences: plans signed and sealed by a Florida-licensed architect or engineer. Wood and chain link fences must be installed per the prescriptive method of the Florida Building Code, 8th Edition, if not designed by an architect or engineer.[1]
- For chain link fences: a completed Chain Link Fence Table.[1]
- All required product approvals, where applicable.[1]
- If piles are required: a completed Special Inspector Form, completed by a Florida-licensed engineer.[1]
- If the fence is located within an easement: a Temporary Structure Affidavit, notarized, filed, and recorded at the Broward County Governmental Center.[1]
- A completed Fence/Wall/Gate Checklist.[1]
- In residential districts, fences and walls facing the street must be set back at least 3 feet from the property line, with continuous hedges, shrubs, and groundcover planted between the property line and the fence (ULDR 47-19.5C). Show this planting on the site plan.[1]
Fees
As published in the city’s fee schedule. Confirm the final amount at submittal — other fees can apply depending on scope.
| Building permit (master, stand-alone, or trade) | $131 minimum, or 1.75% of construction cost[2] |
|---|---|
| State surcharges | DBPR 1% and BCAI 1.5% of total permit fees (minimum $2 each)[2] |
Initial permit fees are now paid when you submit the application. Additional fees may be assessed during review, and the permit is issued once the full balance is paid.[3]
How review works
Submit online through LauderBuild
Fort Lauderdale no longer accepts paper applications or plans for new submissions — everything goes through LauderBuild, the city’s online permit portal. Submission requires a desktop computer; it is not supported on mobile devices.[4]
Pay initial fees at submittal
Initial permit fees are paid at the time the application is submitted.[3]
Intake and plan review
After the initial application intake review, the plans are reviewed digitally. You can track progress, see notes from each city reviewer, and respond to comments in LauderBuild. A fence permit routes through the Building and Zoning review stops, plus Landscaping, Electrical, and Engineering where they apply.[4],[1]
Respond to comments
When resubmitting revisions, don’t upload the whole plan set again — upload only the sheets that changed from the previous submission.[4]
Pay the balance and receive the permit
Once approved, you’re notified of any remaining balance. Approved, stamped plans are released once fees are paid, and online applicants receive an email when the permit is issued. Work may not start until the permit is issued.[4],[3]
Inspections
Inspections are requested through LauderBuild or by phone.[4]
Why applications get rejected
Reasons the city itself calls out in its published guidance.
- Files that don’t follow the city’s required file name and numbering convention are rejected.[4]
- Uploading a document under the wrong document category can cause validation issues or rejection.[4]
- Once the package is submitted for review, you can’t upload additional documents without permission from city staff — so a missing item can’t simply be added afterward.[4]
Frequently asked questions
Do I need a permit to install a fence in Fort Lauderdale?
Yes. The city’s Fence/Wall/Gate Permit Checklist lists a Building permit as the required application, reviewed at the Building and Zoning stops (plus Landscaping, Electrical, and Engineering where they apply). A fence under $7,500 on a single-family property may be eligible for an HB 803 exemption, but only with a written determination from the Building Official before work starts.
How far does a front fence have to be from the property line?
In residential districts, the checklist says fences and walls facing the street must be set back at least 3 feet from the property line, with continuous hedges, shrubs, and groundcover planted between the property line and the fence (per ULDR 47-19.5C). Non-residential districts require the same 3-foot setback plus trees.
Does a PVC or aluminum fence need engineered plans?
Yes. The checklist requires plans signed and sealed by a Florida-licensed architect or engineer for PVC or metal fences. Wood and chain link fences can instead be installed per the prescriptive method of the Florida Building Code, 8th Edition.
How are permit fees calculated in Fort Lauderdale?
The city’s Building Permit Fees schedule (Rev 10, 9/17/2026) charges building permits a minimum of $131 or 1.75% of construction cost, plus state DBPR (1%) and BCAI (1.5%) surcharges on the permit fees. Initial fees are paid at submittal, and any remaining balance is paid before the permit is issued.
Can I submit a paper permit application in Fort Lauderdale?
No. Fort Lauderdale no longer accepts paper applications or plans for new submissions. All new submissions go through LauderBuild, on a desktop computer.
Official sources
- Fence/Wall/Gate Permit ChecklistCity of Fort Lauderdale, Development Services — Building Division · Rev 5, 2/20/2024
- Building Permit FeesCity of Fort Lauderdale, Development Services — Building Services · Rev 10, 9/17/2026
- Florida House Bill 803 (HB 803) Permitting UpdatesCity of Fort Lauderdale, Development Services — Building Services · Rev 3.0, 9/23/2026
- LauderBuildCity of Fort Lauderdale, Development Services
Ask Kodie
Have a question about your fence permit in Fort Lauderdale? Kodie answers from verified Florida Building Code and local requirements, with citations — or upload your plans for a pre-submittal review.
Ask KodieStuck or rejected? We’ll handle it
We prepare, file, and track permits in Fort Lauderdale through to issuance — and take over permits already stuck in review.
Get permit helpThis guide summarizes publicly available documents from the permitting authority and is not legal or code advice. Requirements change — always confirm against the current documents linked above and with the building department before you submit. Florida Construction Permitting is a private permit expediting service and is not affiliated with City of Fort Lauderdale Development Services Department.