Additions, renovations, and remodels in the City of Fort Lauderdale are permitted through the Development Services Department, Building Services. This guide pulls together what the city’s Building Permit Application Checklist, flood-zone substantial improvement guidance, HB 803 guidance, and fee schedule say, with a link to each document so you can check it yourself.
When is a permit required?
- Structural work, electrical, plumbing, mechanical (including air conditioning), and gas work always require a permit regardless of job cost, as does work on a property partly or entirely in a Special Flood Hazard Area, commercial properties, and multifamily properties, condominiums, or apartments.[5]
- Some cosmetic, nonstructural improvements on single-family properties under $7,500 — the city gives interior painting, flooring replacement, cabinet replacement, and drywall repair as examples — may qualify for an HB 803 exemption. It is not automatic: you must submit an exemption request through LauderBuild and receive a written determination from the Building Official before starting work.[5]
- For buildings in a Special Flood Hazard Area: if the cost of the improvement (counting all improvements over a two-year period) equals or exceeds 50% of the building’s market value, it is a “substantial improvement” and the existing building must be brought into compliance with the floodplain requirements for new buildings.[2]
What to submit
- A completed permit application reflecting the total job value and square footage. All sub-permits must be submitted with the master permit.[1]
- For homeowners acting as their own contractor: an Owner Builder Affidavit. The owner must personally appear, complete the affidavit, and sign the building permit.[1]
- Plans drawn to scale, signed and sealed by the designer as required by code (limit plan size to 24 x 36).[1]
- An accurate plot plan and survey (one signed and sealed, one copy). Additions must show proposed elevations on site and on adjacent properties in enough detail to verify there will be no adverse drainage impacts, and the site plan must include pervious and impervious area percentages.[1]
- Any required Special Inspector forms, a Permitting Job Cost Breakdown, and a Dewatering Affidavit where applicable.[1]
- Broward County DER (Development and Environmental Regulation Division) approval for detached additions to single-family or multifamily residences and for additions to non-residential buildings. The permit must be applied for within 90 days of DER approval.[1]
- Broward County Health Department approval for bedroom additions on a septic tank.[1]
- Historic district approval on the application, if applicable.[1]
- For work on existing buildings in a Special Flood Hazard Area: a detailed cost estimate covering all materials and labor (including contractor overhead and profit), an elevation certificate, current exterior photos, and a detailed description of the proposed improvement.[2]
- A recorded Notice of Commencement, provided at permit issuance or before the first inspection. Under Florida law, a copy must be filed before the first inspection when the direct contract is greater than $5,000.[1],[3]
Fees
As published in the city’s fee schedule. Confirm the final amount at submittal — other fees can apply depending on scope.
| Building permit (master, stand-alone, or trade) | $131 minimum, or 1.75% of construction cost[4] |
|---|---|
| State surcharges | DBPR 1% and BCAI 1.5% of total permit fees (minimum $2 each)[4] |
Initial permit fees are now paid when you submit the application. Additional fees may be assessed during review, and the permit is issued once the full balance is paid.[5]
How review works
Submit online through LauderBuild
Fort Lauderdale no longer accepts paper applications or plans for new submissions — everything goes through LauderBuild, the city’s online permit portal. Submission requires a desktop computer; it is not supported on mobile devices.[6]
Pay initial fees at submittal
Initial permit fees are paid at the time the application is submitted.[5]
Intake and plan review
After the initial application intake review, the plans are reviewed digitally. You can track progress, see notes from each city reviewer, and respond to comments in LauderBuild. Additions and remodels are reviewed by each discipline in the scope; all sub-permits are submitted with the master permit.[6],[1]
Respond to comments
When resubmitting revisions, don’t upload the whole plan set again — upload only the sheets that changed from the previous submission.[6]
Pay the balance and receive the permit
Once approved, you’re notified of any remaining balance. Approved, stamped plans are released once fees are paid, and online applicants receive an email when the permit is issued. Work may not start until the permit is issued.[6],[5]
Inspections
Inspections are requested through LauderBuild or by phone.[6]
Why applications get rejected
Reasons the city itself calls out in its published guidance.
- The city’s Building Permit Application Checklist states that an application will not be processed if the required information is not submitted.[1]
- Files that don’t follow the city’s required file name and numbering convention are rejected.[6]
- Uploading a document under the wrong document category can cause validation issues or rejection.[6]
- Once the package is submitted for review, you can’t upload additional documents without permission from city staff — so a missing item can’t simply be added afterward.[6]
Frequently asked questions
Do I need a permit to remodel my kitchen or bathroom in Fort Lauderdale?
If the remodel involves structural, electrical, plumbing, mechanical, or gas work, yes — those always require a permit regardless of cost. Purely cosmetic, nonstructural work on a single-family home under $7,500 (the city gives interior painting, flooring, cabinet replacement, and drywall repair as examples) may qualify for an HB 803 exemption, but only with a written determination from the Building Official before work starts.
What is the 50% rule for remodels in a flood zone?
For buildings in a Special Flood Hazard Area, if the cost of an improvement — counting all repairs, alterations, and additions over a two-year period — equals or exceeds 50% of the building’s market value (excluding land), it is a substantial improvement and the building must be brought into compliance with the floodplain requirements for new construction, including lowest floor elevation. The city’s Flood Section can be reached at (954) 828-6133.
Can a homeowner pull their own addition permit?
Yes, as an owner-builder. The city’s checklist requires an Owner Builder Affidavit, and the owner must personally appear, complete the affidavit, and sign the building permit.
Do I need Broward County approval for an addition?
Broward County DER approval is required for detached additions to single-family or multifamily residences and for additions to non-residential buildings, and the permit must be applied for within 90 days of that approval. Bedroom additions on a septic tank also need Broward County Health Department approval.
How are permit fees calculated in Fort Lauderdale?
The city’s Building Permit Fees schedule (Rev 10, 9/17/2026) charges building permits a minimum of $131 or 1.75% of construction cost, plus state DBPR (1%) and BCAI (1.5%) surcharges on the permit fees. Initial fees are paid at submittal, and any remaining balance is paid before the permit is issued.
Official sources
- Building Permit Application ChecklistCity of Fort Lauderdale, Development Services — Building Services · Rev 11, 6/16/2026
- Substantial Improvement/Substantial Damage Information and AffidavitsCity of Fort Lauderdale, Development Services — Building Services · Rev 2, 09/29/2026
- Florida Statutes §713.135 — Notice of commencement and applicability of lienThe Florida Legislature · 2026 Florida Statutes
- Building Permit FeesCity of Fort Lauderdale, Development Services — Building Services · Rev 10, 9/17/2026
- Florida House Bill 803 (HB 803) Permitting UpdatesCity of Fort Lauderdale, Development Services — Building Services · Rev 3.0, 9/23/2026
- LauderBuildCity of Fort Lauderdale, Development Services
Ask Kodie
Have a question about your addition & remodel permit in Fort Lauderdale? Kodie answers from verified Florida Building Code and local requirements, with citations — or upload your plans for a pre-submittal review.
Ask KodieStuck or rejected? We’ll handle it
We prepare, file, and track permits in Fort Lauderdale through to issuance — and take over permits already stuck in review.
Get permit helpThis guide summarizes publicly available documents from the permitting authority and is not legal or code advice. Requirements change — always confirm against the current documents linked above and with the building department before you submit. Florida Construction Permitting is a private permit expediting service and is not affiliated with City of Fort Lauderdale Development Services Department.