Replacing or installing an air conditioner in the City of Fort Lauderdale is permitted through the Development Services Department, Building Services. This guide pulls together what the city’s A/C Install/Changeout Permit Checklists, HB 803 guidance, and fee schedule say, with a link to each document so you can check it yourself.
When is a permit required?
- An A/C changeout requires a Mechanical permit. A new A/C install requires both a Mechanical and an Electrical permit.[1]
- Florida’s HB 803 small-project exemption does not apply: the city lists mechanical work, including air conditioning systems, among work that still requires a permit regardless of job cost.[4]
- Work may not start until the permit is issued.[5]
What to submit
- For a changeout: dedicated mechanical plans and the A/C data sheet. If more than one unit is being replaced, identify the location and total number of units on the A/C replacement form.[1]
- For a new install: dedicated mechanical plans, heat load calculations, duct sizing calculations, and energy calculations.[1]
- Tie-down details: signed and sealed original engineer anchoring details, or NOA documents, or product approval documents.[1]
- A signed contract showing the total job cost.[1]
- The checklist states that the condenser “must be installed at least 5 feet from the property.”[1]
- A Notice of Commencement must be recorded and displayed at the first inspection if the job exceeds $15,000. Florida law exempts direct contracts under $15,000 to repair or replace an existing heating or air-conditioning system from the Notice of Commencement filing requirement.[1],[2]
Fees
As published in the city’s fee schedule. Confirm the final amount at submittal — other fees can apply depending on scope.
| Building permit (master, stand-alone, or trade) | $131 minimum, or 1.75% of construction cost[3] |
|---|---|
| State surcharges | DBPR 1% and BCAI 1.5% of total permit fees (minimum $2 each)[3] |
Initial permit fees are now paid when you submit the application. Additional fees may be assessed during review, and the permit is issued once the full balance is paid.[4]
How review works
Submit online through LauderBuild
Fort Lauderdale no longer accepts paper applications or plans for new submissions — everything goes through LauderBuild, the city’s online permit portal. Submission requires a desktop computer; it is not supported on mobile devices.[5]
Pay initial fees at submittal
Initial permit fees are paid at the time the application is submitted.[4]
Intake and plan review
After the initial application intake review, the plans are reviewed digitally. You can track progress, see notes from each city reviewer, and respond to comments in LauderBuild. An A/C changeout is a mechanical permit; a new install adds an electrical permit.[5],[1]
Respond to comments
When resubmitting revisions, don’t upload the whole plan set again — upload only the sheets that changed from the previous submission.[5]
Pay the balance and receive the permit
Once approved, you’re notified of any remaining balance. Approved, stamped plans are released once fees are paid, and online applicants receive an email when the permit is issued. Work may not start until the permit is issued.[5],[4]
Inspections
Inspections are requested through LauderBuild or by phone.[5]
Why applications get rejected
Reasons the city itself calls out in its published guidance.
- Files that don’t follow the city’s required file name and numbering convention are rejected.[5]
- Uploading a document under the wrong document category can cause validation issues or rejection.[5]
- Once the package is submitted for review, you can’t upload additional documents without permission from city staff — so a missing item can’t simply be added afterward.[5]
Frequently asked questions
Do I need a permit to replace my AC in Fort Lauderdale?
Yes. The city’s A/C Install/Changeout Permit Checklists require a Mechanical permit for an A/C changeout, and Mechanical plus Electrical permits for a new install.
Is an AC replacement under $7,500 exempt under HB 803?
No. The city’s HB 803 guidance lists mechanical work, including air conditioning systems, among work that still requires a permit regardless of job cost.
Do I need a Notice of Commencement for an AC change-out?
Only above $15,000. The city’s checklist requires a recorded Notice of Commencement, displayed at the first inspection, if the job exceeds $15,000 — consistent with Florida law, which exempts contracts under $15,000 to repair or replace an existing A/C system.
What do I submit for an AC change-out?
A Mechanical permit application with dedicated mechanical plans, the A/C data sheet, tie-down details (sealed engineer anchoring details, NOA, or product approval), and a signed contract with the total job cost.
How are permit fees calculated in Fort Lauderdale?
The city’s Building Permit Fees schedule (Rev 10, 9/17/2026) charges building permits a minimum of $131 or 1.75% of construction cost, plus state DBPR (1%) and BCAI (1.5%) surcharges on the permit fees. Initial fees are paid at submittal, and any remaining balance is paid before the permit is issued.
Official sources
- A/C Install/Changeout Permit ChecklistsCity of Fort Lauderdale, Development Services — Building Services · Rev 8, 9/9/2026
- Florida Statutes §713.135 — Notice of commencement and applicability of lienThe Florida Legislature · 2026 Florida Statutes
- Building Permit FeesCity of Fort Lauderdale, Development Services — Building Services · Rev 10, 9/17/2026
- Florida House Bill 803 (HB 803) Permitting UpdatesCity of Fort Lauderdale, Development Services — Building Services · Rev 3.0, 9/23/2026
- LauderBuildCity of Fort Lauderdale, Development Services
Ask Kodie
Have a question about your ac replacement permit in Fort Lauderdale? Kodie answers from verified Florida Building Code and local requirements, with citations — or upload your plans for a pre-submittal review.
Ask KodieStuck or rejected? We’ll handle it
We prepare, file, and track permits in Fort Lauderdale through to issuance — and take over permits already stuck in review.
Get permit helpThis guide summarizes publicly available documents from the permitting authority and is not legal or code advice. Requirements change — always confirm against the current documents linked above and with the building department before you submit. Florida Construction Permitting is a private permit expediting service and is not affiliated with City of Fort Lauderdale Development Services Department.